Installation inspection connects the delivered equipment to the site systems that make safe first start possible. The handover record should state both what is complete and what remains restricted.

Inputs to prepare

  • Latest approved data sheets, drawings, single-line, settings and control narrative
  • Foundation, anchors, alignment, isolation, access, lifting and housekeeping evidence
  • Cooling, ventilation, fuel or gas, exhaust, drainage and leak/pressure-test records
  • Cable tests, torque, earthing, neutral, phase sequence and protection records
  • I/O, communications, emergency-stop, interlock and cause/effect test records

Decisions to confirm

  • Ready, conditionally ready or not ready for the proposed commissioning activity
  • Permitted first-start and test boundary
  • Open items that can remain without compromising the limited activity
  • Required witness, operator, test load, safety permit and emergency arrangement
  • As-built, settings and deviation records to transfer to operations

Review before release

  • Verify equipment identity against the approved scope
  • Independently confirm normal valve positions, phase sequence and protection settings
  • Retain photographs and test records, not only a signed checklist
  • Classify every punch-list item by consequence and retest need
  • Confirm the receiving owner accepts the handover boundary