Planning Guide

How to Size a Generator Set for Critical Loads

A reviewed guide to load definition, starting behavior, operating duty, site conditions and resilience inputs for critical-load generator selection.

Key Takeaways

  • Build a verified load list with starting data
  • Define duty and redundancy before applying reserve
  • Include environment, installation and future load in the application review

Technical guide introduction

Reliable generator sizing starts with the electrical behavior of the supported system. Running demand alone does not show motor starting, UPS recharge, transformer energization, load steps, redundancy or the required recovery sequence.

Technical planning workflow

Six-Step Project Guide

6 reviewed steps
1

Step 1

Define the Critical Load Profile

Build a verified load inventory with running demand, starting method, sequence and load priority.
Illustrative load inventory — confirm every value for the project
Load / input Running kW Starting factor Sequence Priority
Fire pump 45 3.0 1 Critical
HVAC chiller 75 1.8 2 High
Lighting and controls 35 1.2 3 High
UPS recharge 10 1.0 4 Review
Process motor 20 2.5 5 Critical

Example planning values only. Final load priority and sequence are maintained in the reviewed CMS article record.

2

Step 2

Calculate Power Requirements

Combine running demand, starting allowance, site derating and the agreed design margin.
Required capacity Running demand + starting allowance + design margin Verify transient response, site derating and duty before model release
Illustrative demand build-up Relative planning level; not generator performance data
Define the Critical Load ProfileCalculate Power RequirementsApply Load Factors and Design MarginsSelect the Generator SetValidate PerformancePlan for the Long Term
38% 38% Build a verified load inventory with running demand, starting method, sequence and load priority. 46% 46% Combine running demand, starting allowance, site derating and the agreed design margin. 55% 55% Use diversity only where it is justified and record future-capacity assumptions. 63% 63% Review rating, alternator capability, controls, enclosure and balance-of-plant as one system. 72% 72% Verify transient response, starting sequence, voltage and frequency recovery, and site settings. 84% 84% Confirm service access, fuel autonomy, documentation and the path for future expansion.
3

Step 3

Apply Load Factors and Design Margins

Use diversity only where it is justified and record future-capacity assumptions.

Diversity factor

Largest acceptable load step and starting sequence

Future expansion

Unit count, redundancy, reserve and future-capacity allowance

4

Step 4

Select the Generator Set

Review rating, alternator capability, controls, enclosure and balance-of-plant as one system.
Selection point Standby review Prime review
Operating definition Emergency duty Average duty
Starting capability Largest starting event Load acceptance sequence
Runtime basis Short-duration outage Sustained operating profile
Site conditions Apply project derating Apply application rating basis
CAMDA engineer reviewing generator application information
Application engineering review

Compare the candidate set against the largest load step, motor-starting sequence, site derating, redundancy and future-capacity plan.

5

Step 5

Validate Performance

Verify transient response, starting sequence, voltage and frequency recovery, and site settings.
  1. 1 Reconcile the load list against the current single-line diagram
  2. 2 Check transient performance for the agreed sequence, not an assumed simultaneous start
  3. 3 Apply the applicable rating and site derating basis
  4. 4 Test the failure, recovery and maintenance operating scenarios
Sample validation profile Documented checkpoints across the agreed operating sequence
Reconcile the load list against the current single-line diagramCheck transient performance for the agreed sequence, not an assumed simultaneous startApply the applicable rating and site derating basisTest the failure, recovery and maintenance operating scenarios
Reviewed input 72% Model result 80% Site setting 88% Witness record 96%
6

Step 6

Plan for the Long Term

Confirm service access, fuel autonomy, documentation and the path for future expansion.

Maintenance access

Reconcile the load list against the current single-line diagram

Fuel autonomy

Check transient performance for the agreed sequence, not an assumed simultaneous start

Future capacity

Apply the applicable rating and site derating basis

Final selection checklist
  • Reconcile the load list against the current single-line diagram
  • Check transient performance for the agreed sequence, not an assumed simultaneous start
  • Apply the applicable rating and site derating basis
  • Test the failure, recovery and maintenance operating scenarios
  • Largest acceptable load step and starting sequence
  • Unit count, redundancy, reserve and future-capacity allowance

Explore connected content

Products and Solutions in This Guide

Related products 255

View 254 more related products

Related solutions 1

Related industries 2

View 1 more related industries

Continue your review

About the Author CAMDA Technical Team
Technical Review CAMDA Technical Team

Need Confidence in Your Power-System Selection?

Share your project requirements with CAMDA for technical and commercial review.

Discuss Your Project Request a Quote