Commissioning Readiness Checklist

What the project team should complete before generator start-up, functional testing, load testing and handover.

Key Takeaways

  • Complete installation and safety checks before first start
  • Make current approved records available to the commissioning team
  • Agree test conditions, acceptance criteria and handover responsibilities

Technical guide introduction

Commissioning is most effective when the system, site and records reach a known state before the team arrives. Open interfaces should be visible, owned and controlled rather than discovered during first start.

Technical planning workflow

Six-Step Project Guide

6 reviewed steps
1

Step 1

Complete installation and safety checks before first start

Commissioning is most effective when the system, site and records reach a known state before the team arrives. Open interfaces should be visible, owned and controlled rather than discovered during first start.
Input to confirm Guide context
Complete installation and safety checks before first start Service Guide
Make current approved records available to the commissioning team Service Support
Agree test conditions, acceptance criteria and handover responsibilities 10 minutes
2

Step 2

Make current approved records available to the commissioning team

The public checklist does not replace the approved project commissioning procedure, risk assessment or local safety requirements.
Illustrative planning profile Sequence only ? not generator performance data
Complete installation and safety checks before first start
Make current approved records available to the commissioning team
Agree test conditions, acceptance criteria and handover responsibilities
Approved data sheets, drawings, settings, single-line, control narrative and test procedure
Site access, safety permits, lifting provisions, exclusion zones and emergency arrangements
Cooling, ventilation, fuel or gas, exhaust, electrical, earthing and communications completion records
3

Step 3

Agree test conditions, acceptance criteria and handover responsibilities

What the project team should complete before generator start-up, functional testing, load testing and handover.

Complete installation and safety checks before first start

The public checklist does not replace the approved project commissioning procedure, risk assessment or local safety requirements.

Make current approved records available to the commissioning team

What the project team should complete before generator start-up, functional testing, load testing and handover.

Agree test conditions, acceptance criteria and handover responsibilities

A practical guide to automatic transfer, grid-parallel and multi-generator switchgear requirements, sequences and test evidence.

4

Step 4

Approved data sheets, drawings, settings, single-line, control narrative and test procedure

A practical guide to automatic transfer, grid-parallel and multi-generator switchgear requirements, sequences and test evidence.
Review resource Format Knowledge area Reading time
ATS and Parallel Power System Planning Planning Guide Project Planning 13 min
Preventive Maintenance Planning Service Guide Service Support 10 min
Planning a Gas Power Generation Project Planning Guide Project Planning 11 min
5

Step 5

Site access, safety permits, lifting provisions, exclusion zones and emergency arrangements

How operating hours, calendar time, environment, fuel quality, starts and condition evidence shape a practical generator maintenance plan.
1 ATS and Parallel Power System Planning Planning Guide 2 Preventive Maintenance Planning Service Guide 3 Planning a Gas Power Generation Project Planning Guide
6

Step 6

Cooling, ventilation, fuel or gas, exhaust, electrical, earthing and communications completion records

A practical sequence for defining fuel, electrical duty, site, balance-of-plant, heat use and lifecycle responsibilities before a gas-power proposal.
Service Guide Service Support

Explore connected content

Products and Solutions in This Guide

Related products 4

Related solutions 3

Related industries 3

Continue your review

About the Author CAMDA Technical Team
Technical Review CAMDA Technical Team